RIBA PLAN OF WORK FOR CONSTRUCTION INDUSTRY


RIBA
  • Royal Institution of British Architects

RIBA PLAN OF WORK
  • Pelan Rangka Kerja yang menerangkan proses menguruskan, mereka bentuk projek-projek bangunan, dan mentadbir kontrak bangunan.


 Stage 1 : Preparation 
(a) appraisal - client's objective & feasibility study
(b) design brief - key requirement, procurement method & consultant

Stage 2 : Design
(c) design concept - outline proposal, specification & pre-cost plan
(d) design development - detail concept design & structure, cost plan & planning permission
(e) technical design - component & elements, statutory standards, safety 

Stage 3 : Pre-construction
 (f) information - detail to tender, statutory approval
(g) tender documentation - prepare tender
(h) tender action - evaluate tender, submision & recommend to client

Stage 4 : Construction
 (j) mobilisation - appoint, information & site h/over to contractor
(k) construction to completion - admin. building contract, provision & information

Stage 5 : Use
(l) post practical completion - final inspection, initial occupation & project performance



walaubagaimanapun, RIBA plan of work akan direview mengikut kehendak projek mengikut keadaan dan akan diupdate dari semasa ke semasa (rujuk RIBA plan of work 2013)

references
RIBA plan of work 2007 
RIBA plan of work 2013 

Leave a Reply