RIBA PLAN OF WORK
- Pelan Rangka Kerja yang menerangkan proses menguruskan, mereka bentuk projek-projek bangunan, dan mentadbir kontrak bangunan.
Stage 1 : Preparation
(a) appraisal - client's objective & feasibility study
(b) design brief - key requirement, procurement method & consultant
Stage 2 : Design
(c) design concept - outline proposal, specification & pre-cost plan
(d) design development - detail concept design & structure, cost plan & planning permission
(e) technical design - component & elements, statutory standards, safety
Stage 3 : Pre-construction
(f) information - detail to tender, statutory approval
(g) tender documentation - prepare tender
(h) tender action - evaluate tender, submision & recommend to client
(g) tender documentation - prepare tender
(h) tender action - evaluate tender, submision & recommend to client
Stage 4 : Construction
(j) mobilisation - appoint, information & site h/over to contractor
(k) construction to completion - admin. building contract, provision & information
(k) construction to completion - admin. building contract, provision & information
Stage 5 : Use
(l) post practical completion - final inspection, initial occupation & project performance
walaubagaimanapun,
RIBA plan of work akan direview mengikut kehendak projek mengikut
keadaan dan akan diupdate dari semasa ke semasa (rujuk RIBA plan of work
2013)
references
RIBA plan of work 2007
RIBA plan of work 2013
references
RIBA plan of work 2007
RIBA plan of work 2013